How long does it take to build custom software?

The stages of a custom build, what decides how long each one takes, where projects lose time, what AI changes, and what your side can do to keep it moving

Written by Sean Veldboer, Consultant at CBOS
Published 10 min read

Custom software can take anything from a few weeks for a small tool to over a year for a system that runs a whole business.

Where your project falls depends on its scope, its integrations and the state of your data. It also depends on how quickly your side makes decisions, which can matter as much as how fast anyone writes code. That's why a supplier can't give you an honest date on the first call. What a supplier can tell you early is which of those things will set the pace.

How long does it take to build custom software?

How long it takes to build custom software depends on how long each stage takes, and every stage depends on something different. A custom build moves through roughly these stages, in this order:

Stage What happens What sets how long it takes What it needs from you
Scoping The supplier learns how the process really runs and writes down what will be built How many people, sites and exceptions the process has Time with the people who do the work
Design Screens, workflows and the structure of the data How many roles and rules the system has to handle Quick feedback on each design
Build in short cycles Developers build a piece at a time and show working software The size of the scope and how often it changes A decision-maker at every review
Integration and data Connections to your other systems, and the old data moved across How many systems, and how clean the data is Access to those systems and their owners
Testing and go-live Your people test it on real work, then it goes live How much of the business it touches on day one Testers with time set aside
After launch Fixes, improvements and new features What the business asks for next A list of what matters most

The stages overlap in a well-run project. Design for the second part of the system can start while the first part is being built, and data cleaning can start on day one. What doesn't overlap is a decision nobody has made, which is why what the project needs from you matters as much as what sets each stage's length.

What does a software development timeline look like?

A software development timeline for a custom build is a series of short cycles, each ending in a checkpoint where your people see working software. The Principles behind the Agile Manifesto, written in 2001, put the rhythm plainly: "Deliver working software frequently, from a couple of weeks to a couple of months, with a preference to the shorter timescale."

In practice, that means the first working piece of the system appears well before the whole of it is finished. Your people use that piece, find what's missing and shape what gets built next. The timeline therefore has two dates worth caring about: when the first useful part goes live, and when the last planned part does.

The first date is the one you can bring forward. A system can often go live for one team, one branch or one process before it's ready for everyone. Each release after that adds to something people are already working in, which lowers the risk of a single big go-live.

What decides how long it takes to develop software?

Five things decide how long it takes to develop software for a business, and none of them is how fast the code gets written.

  1. How much of the business it runs. A tool for one team's approvals is a far smaller job than a platform for every branch, depot and role.
  2. What it has to connect to. Each connection to an accounting system, ERP or CRM needs access and a test environment. It also needs someone who knows that system.
  3. The state of your data. Ten years of customer records in three spreadsheets need cleaning and matching before they can move. That work is slow and unglamorous.
  4. Whether it replaces a live system. Replacing a system the business runs on every day means moving over in stages while the old one keeps working.
  5. How quickly decisions get made. Every open question about a rule, a screen or an exception stops part of the work until someone answers it.

The first four are the size of the job, and good scoping measures them. Decision speed is how fast your business can move, and in my experience it can make as big a difference. A system that's well scoped can still run late if each question waits a week for an answer.

Where do software projects lose the most time?

Software projects lose the most time waiting, usually for something the business has to provide. A developer can't build the approval rule until finance agrees what the rule is. The integration can't be tested until the other system's supplier sends test access.

The common waits are easy to recognise:

  • a sign-off that sits with one busy executive
  • two departments that disagree on how a process should work
  • a spreadsheet of old data that nobody owns
  • test access to another system that takes weeks to arrive
  • testers who are pulled back into their day jobs

None of these is a technical problem, and none of them speeds up when the supplier adds people. Fred Brooks managed IBM's OS/360 software project. In The Mythical Man-Month, in 1975, he put it in one line: "Adding manpower to a late software project makes it later." New people need time to learn the system, and the people teaching them stop building while they do.

For a business planning a build, that makes the waits the part of the timeline you can control.

How long does it take to build an app with AI?

How long it takes to build an app with AI depends on what kind of app you mean. An AI app builder can often produce a working prototype of a simple app in an afternoon. That's a useful way to show people an idea.

A system that runs part of a business still needs the stages in the table above. AI speeds up the writing of code, but it leaves the rest of the timeline largely as it was.

The evidence on that speed-up is mixed. In a 2023 lab study by researchers from Microsoft, GitHub and MIT, developers with an AI pair programmer wrote a small web server 55.8% faster. A 2025 study by METR gave 16 experienced developers real tasks on large projects they knew well. With AI tools allowed, they took 19% longer, although they had expected to be faster.

METR returned to the question in February 2026. It said developers are probably more sped up by AI tools now than in early 2025, but that its new data was "only very weak evidence" for the size of that increase.

My reading is that AI will keep shortening the coding stage. A business still has to agree its rules, clean its data, test on real work and sign off. Those stages move at the speed of the business.

Why do software projects run over time?

Software projects run over time because the estimate is made when the least is known. A 2012 study by McKinsey and the University of Oxford covered more than 5,400 IT projects. The large ones, with starting budgets over 15 million US dollars, ran 7 percent over time on average, and software projects carried the highest risk of schedule overruns.

The gap between estimate and reality comes from what surfaces once people use the system. A finance team that sees the first approval screen remembers the exception that happens every month-end. The warehouse finds the one product that's counted in two units. Each of these is real work that nobody could have listed on day one.

A project can deal with that in two ways. Longer scoping finds more of it before the estimate is made. Building in short cycles with a ranked list of work lets each new need be weighed against what's already planned. A good project does both.

What adds time to a software project in South Africa?

Three things add time to a software project in South Africa, and each one is easier to plan for at the start than to discover halfway through.

The first is POPIA. If the system holds personal information about customers or staff, section 19 of POPIA requires reasonable safeguards against foreseeable risks, and regular checks that those safeguards work. Testing access rules and security before go-live is part of the timeline, so it needs its own place in the plan.

Section 21 of POPIA also requires a written contract with any supplier that processes personal information for you. That includes a supplier moving your customer data into the new system. Start the legal review of that contract during scoping, so the data work doesn't wait for it.

The second is local systems. If your build connects to systems common in South Africa, such as Sage, or to a South African bank or payment provider, each connection depends on what access that product allows. CBOS has built Sage integrations for clients' point-of-sale, sales invoices and inventory. For any connection like these, asking for access in the first week saves weeks of waiting later.

The third is the calendar. If your business closes over the December holidays, plan testing and sign-offs around it. A go-live planned for early December with no time to spare can easily become a go-live in February.

How can you shorten a custom software timeline?

You can shorten a custom software timeline by removing the waits, since those are the part your side controls. Four things make the biggest difference:

  • Name one person who can settle questions about the process within a day or two, and give them the time to do it.
  • Pick the process or team where the system will earn its keep soonest, and take that part live first.
  • Have someone start cleaning and owning the old data from day one, while the system is being designed.
  • Ask the owners of every connected system for test access in the first week.

The Agile Manifesto's principles say that "Business people and developers must work together daily throughout the project." Working together every day is more than most custom builds need. The more available your people are, though, the shorter the project.

I'd be wary of any supplier that gives a firm date on the first call. It either hasn't understood the job yet, or it has added a lot of padding to cover what it doesn't know.

How does CBOS work out the timeline for a project?

CBOS works out the timeline for a project by finding the scope before anyone commits to a price or a plan. It starts with a discovery call. A consultancy session follows, which works through your operations to find where new systems are needed and where they aren't.

Where it isn't yet clear what should be built, a more detailed Discovery comes before any fixed price, and that Discovery is generally chargeable. CBOS gives a fixed price only once it's clear what's being built. The written proposal follows.

The build then runs in short cycles. The page on how CBOS designs and builds bespoke software says: "You review working software as it grows, so you can change course early instead of waiting for a big reveal at the end." A system that replaces something live goes in stages too. The Gallo Images case study says: "A planned rebuild, done in stages, is how Gallo Images got onto one platform."

If you're planning a build and want to know what will set its timeline, a discovery call with CBOS is a good place to work it out.

Frequently asked questions

How long does it take to build software?

Building software can take anything from a few weeks for a small tool to more than a year for a system that runs a whole business. Where a project falls depends on its scope, its connections and its data. The speed of decisions on the business's side can matter as much.

How much does it cost to build custom software?

The cost of custom software is driven by much the same things as its timeline. These include how much of the business it runs, what it connects to and how settled the process is. Those drivers are set out in what decides the cost of custom software in South Africa. A reliable figure comes only after the scope is clear.

What is the 40/20/40 rule in software engineering?

The 40/20/40 rule in software engineering is an informal rule of thumb for splitting a project's effort. It puts about 40% on planning and design, 20% on writing code and 40% on testing. No standards body sets it. Fred Brooks gave a similar split in The Mythical Man-Month in 1975, with a sixth of the schedule for coding. Both make the same point, which is that coding is the smaller part of the work.

Can adding more developers make a software project faster?

Adding more developers can make a software project faster if they join early and the work splits cleanly into separate parts. Added late, they usually slow it down, because the existing team has to stop and bring them up to speed. Brooks's law, from 1975, covers the second case: "Adding manpower to a late software project makes it later."

Is a fixed price also a fixed date?

A fixed price fixes the cost of the scope written into the contract. Whether it also fixes a date depends on what the contract says. Anything added after signing goes through a change request, which can move the price and the timeline. CBOS gives a fixed price only once it's clear what's being built. The guide to fixed price vs time and materials sets out who carries the risk under each.

How long does it take to move from spreadsheets to software?

How long it takes to move from spreadsheets to software depends mostly on the spreadsheets. A process with clear rules and tidy data can move quickly. One with years of history and rules that live in people's heads takes longer. The data and the rules have to be agreed first. Moving one process at a time is usually faster than moving everything at once.

About the author

Sean Veldboer

Consultant at CBOS

CBOS designs and builds platforms, portals, mobile apps and integrations for companies in South Africa and around the world, and has done since 2014. More about CBOS

Have a project like this in mind?

Book a discovery call and we'll look at how your operation runs, then put the scope and price in a written proposal.