Fixed price vs time and materials: which suits your software project?

Who carries the risk in each contract, when each one fits, the hybrid models in between, and what to write into the contract before you sign

Written by Sean Veldboer, Consultant at CBOS
Published 10 min read

Fixed price vs time and materials decides who pays for a wrong estimate: the supplier (fixed price) or you (time and materials).

That one difference shapes the rest of the contract. A fixed price suits a software project whose scope can be fully written down before work starts, and time and materials suits work that will change once people see it. A partly understood project suits a hybrid. In all three, the risk falls when someone senior checks the scope before signing, which is the work of CBOS's strategic consulting team.

What is the difference between fixed price and time and materials?

A fixed price contract sets one figure for an agreed scope. The supplier delivers that scope for that figure. A time and materials contract sets the rates for people's time at the start, plus any materials such as licences or hosting. The final cost is whatever the work used. The two compare like this:

Fixed price Time and materials Hybrid
What's agreed up front The scope and the total The rates, and usually a budget A fixed first phase, or a cap
Who carries the estimate risk The supplier, who prices it in You Shared
When the scope changes A change request, priced separately The work goes on the list and into the hours Into the next phase, or within the cap
Your time on the project Mostly at the start and at sign-off Every week or two Heavy at the start, then regular
Suits A scope that can be written down completely A product that will change as people use it A process that's partly understood

Lóren Rose, COO of the South African software house Global Kinetic, described the split to ITWeb in May 2023. "In fixed-cost projects, risk lies with the supplier so they will have to assume the cost of overrun," she said. "In time and materials projects, the risk lies with the customer, so they will need to assume the cost of overrun."

Neither model removes the risk, and software carries a good deal of it. A 2012 study by McKinsey and the University of Oxford of more than 5,400 IT projects found that, among large IT projects, software projects run the highest risk of cost and schedule overruns.

How does a fixed price contract work for software?

A fixed price contract turns the estimate into the supplier's problem. Before anyone writes code, the supplier needs a specification detailed enough to price. It covers every screen, rule, report and integration, and the data that has to move from the old system. Writing it can take several weeks, and your people will spend much of that time answering its questions. Our article on how long it takes to build custom software shows where that time sits in the whole project.

Because the supplier carries the cost of a wrong estimate, the quote includes a margin for that risk. You're paying for certainty. That's a fair trade when the board needs one number and the scope really is settled.

After signing, anything outside the specification becomes a change request, with its own cost and its own approval. In software, a great deal only surfaces once people use the system. A finance team that sees the first approval screen will remember the exception that happens every month-end. That exception now needs a quote.

Rose made the same point in the ITWeb story: "Change is inevitable and the cost and overhead of managing that change in fixed-cost projects is what creates friction that leaves both customers and employees unhappy."

A fixed price also changes the supplier's incentives. A supplier losing money on the job has every reason to deliver the letter of the specification and no more. The urge to build the best version of the system weakens as the budget runs down.

How does a time and materials contract work?

A time and materials contract pays for the work as it happens. You agree the rates for each role at the start, usually with a monthly budget. The supplier then bills for the hours used. The team builds in short cycles and shows working software at the end of each one. You decide what gets built next.

This is the way of working the Manifesto for Agile Software Development described in 2001. It valued "Customer collaboration over contract negotiation" and "Responding to change over following a plan". Nobody has to predict the whole system on day one. Work starts sooner, and money goes into what turns out to matter.

The price of that flexibility is that the total isn't known until the end. The risk of a slow team or a wandering scope sits with you. So time and materials needs things on your side that a fixed price doesn't:

  • a product owner who can make decisions every week or two
  • a ranked list of what to build next, kept up to date
  • a monthly spend report against the budget, with hours by role
  • a review of working software at the end of every cycle

Without those, time and materials becomes an open tab. With them, you can see what you're paying for. You can also stop or change direction at the end of any cycle.

When to use a time and material contract

Use a time and material contract when the requirements will change once people see the software. You also need to be able to give the project regular attention. In practice that covers:

  • a new product or customer portal, where users' reactions will reshape it
  • a process that has lived in spreadsheets and email, because nobody has written all of its exceptions down
  • an integration with an older system whose documentation can't be trusted
  • work after launch, such as improvements and new features, which arrives in small pieces
  • anything involving AI on your own data, where the first tests decide what's worth building

Time and materials is a poor fit in one case. If nobody in your business can give the project an hour or two a week, the work will drift. A fixed price with a tightly written scope may serve you better, even at a higher quote.

When does a fixed price suit a software project?

A fixed price suits a software project you could hand to three suppliers and get three quotes for the same thing. That usually means one of these:

  • a small, well-understood piece of work, such as a report, a form or one integration with documented systems
  • a project the supplier has built many times before, so their estimate rests on experience
  • a deadline set from outside, such as a regulation, where the rule sets most of the scope
  • a first discovery or design phase, priced on its own, whose result is the specification

The last one is often the most useful. A short fixed phase can end in a written scope, screen designs and an estimate. That gives you something concrete to judge before the larger commitment.

Fixed fee vs time and materials: is one cheaper?

Neither fixed fee nor time and materials is cheaper as a rule. They price the same uncertainty in different places. A fixed fee puts it into the supplier's risk margin and into change requests. Time and materials leaves it in the hours, where you can see it and control it if you manage the work.

For a clearly defined project, a fixed fee can come out cheaper, because the margin is small and few changes arrive. For a project with a lot to learn along the way, time and materials can cost less in the end. You pay only for what gets built, and you can stop building what isn't needed.

The fair comparison is between two whole proposals. Look at what each covers, what each leaves out, and what each says happens when the scope moves. What drives the size of either number is covered in what decides the cost of custom software in South Africa. If you haven't yet decided whether to build at all, start with build vs buy for business software.

What are the hybrid options between fixed price and time and materials?

Hybrid options keep certainty where you can have it and flexibility where you need it. Three suit software work:

  1. Phased. A fixed price discovery phase produces the scope. Each build phase is then estimated and confirmed before it starts, so you judge each phase before committing to the next.
  2. Capped time and materials. The work is billed on time and materials, with a "not-to-exceed" ceiling agreed up front. Nearing the cap means cutting the items at the bottom of the ranked list.
  3. A fixed monthly team. You pay a fixed amount each month for an agreed team and choose what it works on. Spend is predictable and the scope stays open.

A hybrid only works when the contract says when one model hands over to the other. It should say what ends the fixed phase, who agrees the next estimate, and what happens to unfinished work at the cap.

What goes into a fixed price vs time and materials contract?

A fixed price vs time and materials contract needs some different clauses and some shared ones. A fixed price contract should carry:

  • the full specification as an annex
  • a change request process, with turnaround times
  • acceptance criteria for each deliverable
  • payment milestones tied to those deliverables

A time and materials contract should carry the rates by role and the budget. It should say how often you'll see spend against that budget, what any cap is, and how long each cycle runs. It should also give you the right to stop at the end of any cycle, with the work done so far handed over.

Both kinds should say who owns the source code and when it passes to you. They should cover support and fixes after launch, and how the supplier hands over if the relationship ends. The points above are what to look for, not legal advice, so have your own lawyer read the contract before you sign.

What should a South African business check before signing either?

A South African business should check two things before signing either model. The first is POPIA. A supplier that hosts the system, supports it or handles your data during migration is an operator under the Act when it processes personal information for you.

Section 21 of POPIA requires a written contract with every operator. That contract must make the operator keep the security measures in section 19. The Act also makes the operator tell you immediately when there are reasonable grounds to believe personal information has been accessed or acquired without authority, and the contract should say how and to whom. Both apply under either model.

The second is currency. Say an offshore supplier bills time and materials by the hour in dollars or euros. The rand cost then moves with the exchange rate as well as with the hours.

A fixed price in rand takes the currency risk away. A fixed price in dollars doesn't, and foreign-currency time and materials adds a second unknown to the hours. Ask which currency the rates are in before comparing proposals.

How does CBOS lower the risk before either model is signed?

CBOS lowers the risk by finding the scope before anyone prices it. Every CBOS project starts with a discovery call. A consultancy session follows, which works through your operations to find where new systems are needed and where they aren't. The written proposal comes after it, built on what it found. A better scope narrows the estimate in either model, which makes the choice between them easier.

CBOS only gives a fixed price once it's clear what's being built. Where the scope isn't clear yet, a detailed Discovery comes first, and that Discovery is generally chargeable. It costs less than pricing a build on guesses and arguing about change requests later.

The build runs in short cycles, and you review working software as it grows. The page on how CBOS runs a bespoke build sets this out. Those regular reviews are what keep time and materials under control. Under a fixed price, they catch a misunderstanding early.

You may already have a proposal from another supplier. CBOS's strategic consulting team can review that proposal and challenge it before you commit.

If you're weighing a fixed price against time and materials for your own project, a discovery call with CBOS is a good place to work out which suits it.

Frequently asked questions

What is fixed fee vs T&M?

Fixed fee and fixed price mean the same thing. It's one agreed figure for an agreed scope, with the supplier carrying the cost of a wrong estimate. T&M is short for time and materials. You pay agreed rates for the time and materials the work uses, and the final total is known only at the end.

What does "fixed price" mean?

In a software project, "fixed price" means the supplier delivers a written scope for one total figure, however many hours it takes. The price stays fixed only for that scope. Anything added or changed after signing goes through a change request with its own cost.

Is time and materials the same as cost plus?

Time and materials and cost plus are close, but they differ in how the supplier's profit is paid. Under time and materials, the profit is built into the agreed hourly rates. Under cost plus, the supplier is paid its actual costs plus a separate agreed fee.

Can a time and materials contract have a maximum price?

A time and materials contract can have a maximum price through a "not-to-exceed" clause, which caps what you'll spend. Pair the cap with a ranked list of work. Then, if the budget runs low, the least important items are the ones left out.

Can you switch from time and materials to fixed price?

You can switch from time and materials to fixed price once the scope is clear enough to quote. A common pattern is a short discovery phase, then a fixed price for a well-defined build, then time and materials for improvements after launch. Write the switch points into the contract from the start.

About the author

Sean Veldboer

Consultant at CBOS

CBOS designs and builds platforms, portals, mobile apps and integrations for companies in South Africa and around the world, and has done since 2014. More about CBOS

Have a project like this in mind?

Book a discovery call and we'll look at how your operation runs, then put the scope and price in a written proposal.

Legacy system modernisation in South Africa, without stopping the business
The approaches, how to move one piece at a time while the old system keeps working, and what POPIA and local hosting add to the plan